Services Asquith Golf Club Projects About Contact Call 0413 998 693
← All projects Project · Double Bay

Double Bay - Lancaster Gate

A 12 unit block rebuilt from the ground up: new plumbing, new walls and more than 450 sqm of new concrete.

A 12 unit block in Double Bay with failing plumbing, a damaged retaining wall and old driveways throughout. We pulled it all out, replaced the stormwater and sewer, rebuilt the wall and poured the new concrete. Every stage is below, in the order we did it.

Out with the old

This 12 unit block in Double Bay needed all its driveways, paths and stairs removed so the plumbing (sewer and stormwater) could be redone across the whole block. More than 450 sqm of concrete, with very little room to move.

Damaged wall removal

This damaged wall was hanging on by a thread. There was a six car carpark on top of it, which had to be removed and replaced. Our engineer came up with a new approved design and down it came.

Piers

To meet the engineer's requirements we had to pier into solid rock before placing the steel cages and formwork. The engineer set the pier diameter and spacing, and steel went into each pier for extra strength.

Plumbing

The plumbing here looked like something from the antique roadshow. All the old pipes and systems had to be replaced before the steel and concrete went in. To avoid blockages and allow camera access in future, we added a number of extra inspection points for maintenance.

Pits

The old pits had to go, and new pits went in to handle all the extra stormwater. Concrete pits were specified for a job this size.

Steel

Once the plumbing is in, the prep work starts for the concrete. A blue metal base for drainage, plastic, steel and chairs were installed ready for the pour.

Waterproofing

Just as important as the drainage and plumbing, the new walls had to be waterproofed before the pour. Three layers of waterproofing were painted on the back of the walls, then new membrane with attached geocloth was pinned to the walls, and aggregate, agg lines and more geocloth backfilled the walls before pouring.

Concrete

With the plumbing, pits, steel and drainage in, it was time for the concrete. More than 70 cubes to cover the job.

Old to new

A quick snapshot of our biggest concrete (and plumbing) job to date.

Your project could be next.

Tell us what you're planning and we'll get back to you with a quote.